High-voltage transmission lines head to Versant Power's substation in Orrington, Maine, as seen on Oct. 15, 2026. Photo by Erin Rhoda.

banner that says by Delger Erdenesanaa, the environment reporter for the maine monitor

$130 million refund to Maine customers in limbo as electric utilities appeal order to cut profits


Electric utility companies’ profits are under close scrutiny from ratepayers, advocacy groups and regulators these days, including in Maine. But utilities are fighting to maintain their higher returns, citing a need to attract investment to maintain reliable infrastructure, especially as climate change puts pressure on the grid. 


Because these companies have monopolies over their service areas and don’t face competition, the returns they can make on their investments are regulated. Deciding how much profit is enough, however, can take months or even years of debate and litigation.


Central Maine Power’s latest distribution rate proposal, which includes bumping up the company’s return on equity, has taken center stage this year. As state regulators very publicly review that request, other regulation affecting customers’ electric bills has been happening more quietly in the background.


State and federal agencies have taken steps to try and limit profits on the transmission side. Earlier this year, the Federal Energy Regulatory Commission ordered New England transmission utilities to refund more than $1.5 billion to customers after finding that the companies’ authorized returns were set too high.


The utilities are pushing back, and litigation is ongoing. More recently, Maine officials asked the federal regulator to get rid of an incentive that also boosted potential returns for utilities — and are being sued by some of the companies in response.

READ THIS STORY
banner that reads "on our radar"

On the water utility side of things, Penelope Overton at the Portland Press Herald reported that the Greater Augusta Utility District is suing four paper mills on the Kennebec River.


The utility claims the mills polluted the watershed with per- and polyfluoroalkyl substances, or PFAS, and should shoulder the cost of treating water to remove these “forever chemicals” — $2 million in this case.


The Greater Augusta Utility District is asking the federal court to hold Sappi, Huhtamaki, Kimberly-Clark and American Tissue Corp. responsible for this cost, rather than ratepayers and taxpayers.

banner ad for the wells reserve at laudholm.
banner that reads from the maine monitor

Eastport files motion to intervene in underwater data center case | Monitor Local


Paris Select Board puts data center development on hold | Monitor Local

banner that reads in other maine environment news

The following stories are from other newsrooms. While The Maine Monitor does not place its content behind a paywall, some newsrooms we link to below may. Paywalled stories are followed by a ($). We encourage you to consider supporting local Maine newsrooms.

Maine race for Senate, climate and environment | Living on Earth


Maine’s tallest mountain is greening faster than others in New England | Portland Press Herald ($)


Maine agency fines Fryeburg Solar $204K for damaging environment | Portland Press Herald ($)


Exposure to South Portland tank emissions increases cancer, chronic illness risks, report says | Portland Press Herald ($)


5 large whales found entangled off the Maine coast in 2025 | Portland Press Herald ($)


‘Thousands’ of dead fish discovered along Androscoggin River | The Times Record ($)


Court rules CLF's case against Cooke Aquaculture can proceed | Quoddy Tides


A punishing drought has neighbors pointing fingers at Maine’s Poland Spring | Boston Globe ($)


Ending the federal 'roadless' rule could threaten these Maine forests | Maine Public


Maine regulators reject CMP's temporary rate hike | Maine Public


CMP delays project that could have improved service for thousands of homeowners | News Center Maine


CMP shares northern Maine transmission route with legislators | Bangor Daily News ($)


Renewed fossil fuel investments raise prices, pollution in Maine | Public News Service


Conservationists seek fair menhaden reallocation for Atlantic states | Public News Service

click the banner to view the maine monitor's voter guide

Have feedback, a correction or know of something we should look into? Send it to our newsroom. You can also email The Monitor's editors: editors@themainemonitor.org.  


The Maine Monitor is a publication of the Maine Center for Public Interest Reporting, an independent and nonpartisan nonprofit news organization that produces investigative journalism. We believe news is a public good and keep our news free to access. We have no paywall and do not charge for our newsletters. If you value the reporting we do for Maine, please consider making a donation! We cannot do this reporting without your support.

DONATE NOW
banner that states the maine monitor is part of the trust project, an international consortium of news organizations implementing transparency standards. tap to learn about the monitor's editorial standards.

Manage preferences | Update email address


Email Marketing by ActiveCampaign